PMP?每日一練試題內(nèi)容(2023/2/4)
試題1
Because there are too many conflicting discussions for the project deliverables,a project for the implementation of the new system encountered a problem when it is published, leading to the project manager to leave the company. A new project manager is assigned to the pro1ect. What is the new project manager should first take action?查看答案
試題參考答案:D
試題解析與討論:www.xcpkj.com/st/484233276.html
試題2
在設(shè)計(jì)任務(wù)100%完成之前,項(xiàng)目經(jīng)理正在制定交付時(shí)間長(zhǎng)的物品的采購(gòu)計(jì)劃,項(xiàng)目經(jīng)理應(yīng)使用哪個(gè)緊前關(guān)系繪圖法(PDM)依賴關(guān)系?查看答案
試題參考答案:B
試題解析與討論:www.xcpkj.com/st/4622611286.html
試題3
項(xiàng)目章程準(zhǔn)之后,項(xiàng)目經(jīng)理開始使用儲(chǔ)備分析進(jìn)行預(yù)算工作,哪些文件支持這項(xiàng)工作?查看答案
試題參考答案:B
試題解析與討論:www.xcpkj.com/st/464776129.html
試題4
A project team is developing the work breakdown structure (WBS)for a project. Completion of the project is contingent upon delivery of multiple subprojects. To move forward wit h the WBS, what should the project team do?查看答案
試題參考答案:B
試題解析與討論:www.xcpkj.com/st/4814910711.html
試題5
某項(xiàng)目已進(jìn)行了9個(gè)月,并預(yù)計(jì)將在3個(gè)月內(nèi)結(jié)束。使用掙值管理方法,掙值/計(jì)劃價(jià)值的比率大于1。請(qǐng)問目前項(xiàng)目是什么狀態(tài)?()查看答案
試題參考答案:D
試題解析與討論:www.xcpkj.com/st/4893625965.html
試題6
A customer is surprised about a change made to a deliverable. The project manager explains that this change was communicated via email,and that there is a possibility that the em ail has not yet been read. What should the project manager h ave done differently?
客戶對(duì)某個(gè)可交付成果的變更感到驚訝.項(xiàng)目經(jīng)理解釋說,這一變更是通過電子郵件溝通的,客戶有可能還沒有閱讀電子郵件.項(xiàng)目經(jīng)理事先應(yīng)該采取哪—項(xiàng)不同做法?
A、Ensured that the communication cycle was complete d, and asked the customer to confirm receipt of the information 確保已完成溝通循環(huán),并要求客戶確認(rèn)已收到信息
B、Sent a follow-up email to determine if the customer re ad the first email,and obtained a read confirmation 發(fā)送一封跟進(jìn)電子郵件已確定客戶是否閱讀了第一封電子郵件,并獲得已閱讀確認(rèn)
C、Called,rather than emailed,the customer with all details,and asked them to send a confirmation給客戶打電話(而不是通過電子郵件)告訴客戶所有詳細(xì)信息,并要求他們發(fā)送確認(rèn)信
D、Developed the communications management plan 制定溝通管理計(jì)劃
查看答案
試題參考答案:D
試題解析與討論:www.xcpkj.com/st/478058105.html
試題7
根據(jù)項(xiàng)目計(jì)劃,項(xiàng)目的狀態(tài)如下∶按每小時(shí)28美元的勞動(dòng)費(fèi)率,工作1000小時(shí),計(jì)劃花費(fèi)28000美元。監(jiān)控成本時(shí),項(xiàng)目經(jīng)理確定成本績(jī)效指數(shù)為0.8。項(xiàng)目的實(shí)際成本為40000美元。項(xiàng)目的進(jìn)度偏差是多少?()查看答案
試題參考答案:B
試題解析與討論:www.xcpkj.com/st/4892719590.html
試題8
一個(gè)項(xiàng)目可交付成果延期并錯(cuò)過了截止日期,團(tuán)隊(duì)領(lǐng)導(dǎo)為這些問題責(zé)備初級(jí)團(tuán)隊(duì)成員。項(xiàng)目經(jīng)理應(yīng)該怎么做?查看答案
試題參考答案:D
試題解析與討論:www.xcpkj.com/st/4632821134.html
試題9
The asphalt highway project that the project manager is managing is 50% complete. The PM planned on having 4,000 square yards of asphalt placed by now,but in actuality. They've finished placing 8,000 square yards. The estimated cost forth is work was $1 per square yard. The actual cost for this work is $ 8,000.查看答案
試題參考答案:B
試題解析與討論:www.xcpkj.com/st/4896817701.html
試題10
敏捷團(tuán)隊(duì)完成了產(chǎn)品開發(fā)階段,并核實(shí)所有測(cè)試均已通過,但客戶報(bào)告對(duì)質(zhì)量和性能不滿意。若要避免這種情況,敏捷項(xiàng)目團(tuán)隊(duì)?wèi)?yīng)該在產(chǎn)品發(fā)布之前做什么?查看答案
試題參考答案:D
試題解析與討論:www.xcpkj.com/st/5252520429.html
信管網(wǎng)訂閱號(hào)
信管網(wǎng)視頻號(hào)
信管網(wǎng)抖音號(hào)
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評(píng)論 查看完整評(píng)論 | |