PMP?每日一練試題內(nèi)容(2023/3/28)
試題1
An organization initiates a large project in a developing country. The project manager,who is also the local stakeholder,is very supportive of this project. During project execution,the project manager is transferred to another country. T he new project manager is less supportive of the project because it uses many local resources that could be focusing on other daily responsibilities. What document should the project manager review?查看答案
試題參考答案:B
試題解析與討論:www.xcpkj.com/st/477947567.html
試題2
A seller is awarded a contract to build a pipeline. The contract terms and conditions require that a work plan be issued for the buyer's approval prior to commencing work,but the seller fails to provide one. Which of the following is the BEST thing for the buyer's project manager to do?查看答案
試題參考答案:C
試題解析與討論:www.xcpkj.com/st/4877514171.html
試題3
團隊成員無法就新項目的可交付成果達(dá)成一致意見項目經(jīng)理獲得團隊對分階段實施方法的一致意貝.以便所有可交付成果在不同項目階段實施,項目經(jīng)理使用的是哪種沖突管理技巧?查看答案
試題參考答案:D
試題解析與討論:www.xcpkj.com/st/4980024271.html
試題4
為了更好的聞述個人、組織和部門的行為方式,讓團隊有一個統(tǒng)一的規(guī)范,項目組應(yīng)該使用:查看答案
試題參考答案:A
試題解析與討論:www.xcpkj.com/st/4260024298.html
試題5
An assumption used to develop the project management plan proved invalid during the execution phase.As a result,the next project milestone will be unmet. What should the project manager do first to get the project back on track查看答案
試題參考答案:D
試題解析與討論:www.xcpkj.com/st/4794118001.html
試題6
在項目關(guān)鍵執(zhí)行階段,一名高級行業(yè)專家通知項目經(jīng)理他即將離開公司。該專家是擁有本階段所需知識的唯一一名團隊成員。項目經(jīng)理應(yīng)首先查閱哪份文件?查看答案
試題參考答案:B
試題解析與討論:www.xcpkj.com/st/49868363.html
試題7
在風(fēng)險識別過程,一個項目經(jīng)理和其他相關(guān)方用了很多的方法識別了很多的風(fēng)險,項目經(jīng)理確認(rèn)所有的風(fēng)險都已經(jīng)搞清楚并且知道了觸發(fā)器。之后,在風(fēng)險應(yīng)對計劃的制定過程中,他把所有識別的風(fēng)險——決定減輕的策略。他犯了什么錯誤?查看答案
試題參考答案:B
試題解析與討論:www.xcpkj.com/st/475503803.html
試題8
項目團隊正在制定風(fēng)險管理計劃,本工作采用何種工具和方法確定風(fēng)險成本因素,并為項目預(yù)算和時間表覆蓋的活動安排進(jìn)度?查看答案
試題參考答案:A
試題解析與討論:www.xcpkj.com/st/4772814674.html
試題9
A project team must develop new technology for a project which has no previous data available. The project manage r wants to determine the cost of developing and prototyping this new technology.What should the project manager use to estimate the project's costs?查看答案
試題參考答案:B
試題解析與討論:www.xcpkj.com/st/465674717.html
試題10
一個項目已經(jīng)支出350萬美元,現(xiàn)在已完成400萬美元的工作,該項目的計劃價值(PV)為800萬美元,主題專家(S ME)估算還需要600萬美元來完成該項目,完成該項目的技術(shù)方法不再有效,當(dāng)前的完工估算(EAC)是多少?查看答案
試題參考答案:B
試題解析與討論:www.xcpkj.com/st/462504201.html
信管網(wǎng)訂閱號
信管網(wǎng)視頻號
信管網(wǎng)抖音號
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評論 查看完整評論 | |