試卷名稱 信息系統(tǒng)項目管理師-pmp練習(xí)題-2
考試中心《信息系統(tǒng)項目管理師-pmp練習(xí)題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

After creating WBS, the project manager initiated through brainstorming process to identify risks. This process identified a number of potential risks, What should the project manager do ?
A、Change the scope of the project in order to avoid risks.
B、Accept the risk and expected values included in the project budget.
C、Identify potential response.
D、Implementation of the work program in order to avoid the risk.