国产精品久久久久久免费免熟,五月婷婷激情综合网,欧美三级视频网站,一级少妇淫片,国产精品女教师av久久,啪啪免费视频,wwww黄色片

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-3
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-3》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The plan for a technological restructuring project is in the planning phase for months and within that time, the technology has advanced significantly. The project is scheduled to begin this month, and the scope management plan must be updated to reflect the changes in the technology. The project manager must elaborate on the potential changes to the project scope with the key stakeholders.  The project manager understands that the level of uncertainly for the project will do which of the following ?
A、Stay at the level that was anticipated and planned for.
B、Initially increase and then decrease.
C、Increase.
D、Decrease.


相關(guān)試題

推薦文章