国产精品久久久久久免费免熟,五月婷婷激情综合网,欧美三级视频网站,一级少妇淫片,国产精品女教师av久久,啪啪免费视频,wwww黄色片

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(1)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(1)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The project manager is briefing management on project status and identifies a negative schedule variance but a positive cost variance. Which of the following conclusion is reasonable?
A、The project is behind schedule but may be brought back on schedule by adding resource
B、The project is ahead of schedule but over budget and needs further investigation
C、The project is behind schedule, over budget and merits serious concern
D、The project is ahead of schedule, under budget and progressing with no obvious issues


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容