国产精品久久久久久免费免熟,五月婷婷激情综合网,欧美三级视频网站,一级少妇淫片,国产精品女教师av久久,啪啪免费视频,wwww黄色片

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱(chēng) 2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(2)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(2)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A project is made of three activities. Activity A is lasting for 5 weeks, activity B is lasting for 6 weeks, activity C is lasting for 7 weeks, the taxis is A-B-C. While, it will take 1 week for resource distribution of activity B, and activity C will start in one week after the beginning of activity B. What is the shortest time limit for this project?
A、12 weeks
B、13 weeks
C、14 weeks
D、16 weeks


相關(guān)試題

推薦文章