The project manager observes that some project team, members begin to work together and adjust work habits, however, they do not trust each other. The project manager may conclude which of the following about the team?
A、it is in the norming stage of development and will most probably move on the performing stage
B、It is in the norming stage of the development and will most probably slip back to the storming stage
C、It is in the storming stage of development and will most probably move on to the norming stage
D、It is in the storming stage of the development and will most probably slip back to the forming stage