試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(4)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

During project execution, the customer indicates that there will be limited access to the test facility due to several concurrent projects. This change may lead to schedule delays. To minimize the negative impact, what should the project manager do next?
A、Advise the customer about schedule creep.
B、Check the risk register for approved corrective actions.
C、Perform a risk analysis.
D、Update the project schedule according to this change.