試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(4)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A project manager for the seller is told by her management that the project should do whatever possible to be awarded incentive money. The primary objective of incentive clauses in a contract is to:
A、reduce costs for the buyer.
B、help the seller control costs.
C、synchronize objectives.
D、reduce risk for the seller by shifting risk to the buyer.