During the project's construction phase, a supplier has a fire and the supply of raw material is delayed by a week, The project manager identified the risk of a delay and included it in the plan .After the occurrence of the event, what should the project manager do first?
A、Carry out risk response planning
B、Ask for an extension of the project due to delay
C、Update the project baseline
D、Update the risk register