When a project manager approaches the end of their company’s big project, the company’s organizational structure, objective and Strategies have changed. What should the project manager take from the following methods?
A、Speak with the line one manager to ensure the whole resources should continue to complete the task which assigned before.
B、Check if there is budget available to continue the project following the master schedule.
C、Disregard the change in goals and strategies and continue to run the end.
D、Inquire with the project sponsor as to whether or not the project still fits the company’s Strategies.