試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(7)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(7)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

A company adopted globalization as a risk-mitigation strategy to deal with shrinking growth prospects in developed economies. During the risk review board meeting, the project manager realizes that the company’s global revenues are not growing at the expected rate. Where is the project manager in the project’s life cycle?
A、Risk planning phase
B、Execution of risk response
C、Control risks phase
D、Process of closing risk register