66題: Security vulnerability are considered a type of ( )
A.technical risk
B.management risk
C.organizational risk
D.commercial risk
答案解析與討論:
www.xcpkj.com/st/6306911581.html第
67題: ( )is the basis of information .
A. Data
B. wisdom
C.concepts
D. knowledge
答案解析與討論:
www.xcpkj.com/st/6307010573.html第
68題: A project is a ( ) endeavor undertaken to create a unique product , service , or result .
A.static
B.permanent
C.temporary
D.renting
答案解析與討論:
www.xcpkj.com/st/6307119120.html第
70題: 關(guān)于商標(biāo)法,( )是不正確的。
A.商標(biāo)十年到期后,再續(xù)展有效期是5年
B.商標(biāo)在相當(dāng)范圍內(nèi)被大眾熟知,如果商標(biāo)持有人覺得(侵權(quán)),可以申請(qǐng)馳名商標(biāo)保護(hù)
C.商標(biāo)有效期到期前十二個(gè)月內(nèi)需提交延期申請(qǐng)
D.商標(biāo)法于2019年4月修訂
答案解析與討論:
www.xcpkj.com/st/6315816796.html第
71題: ( )is the correct full name for the “OPM”
A. Organizational Project Management
B. Operational Performance Management
C. Optimized Portfolio Management
D. Outcome Performance Management
答案解析與討論:
www.xcpkj.com/st/631599882.html第
72題: 關(guān)于進(jìn)度管理的描述,不正確的是( )。
A.項(xiàng)目開展過程中,關(guān)鍵路徑可能會(huì)發(fā)生變化
B.關(guān)鍵路徑上的活動(dòng)的總浮動(dòng)時(shí)間和自由浮動(dòng)時(shí)間都為0
C.資源平滑技術(shù)通常會(huì)導(dǎo)致項(xiàng)目關(guān)鍵路徑變長
D.定義活動(dòng)、排列活動(dòng)順序、估算活動(dòng)持續(xù)時(shí)間可以由一個(gè)人在較短時(shí)間內(nèi)完成