試題1
某項(xiàng)目受各種因素的影響已停工半年,由于市場(chǎng)環(huán)境變化,該項(xiàng)目已不再具備商業(yè)價(jià)值。近期臺(tái)風(fēng)導(dǎo)致項(xiàng)目外墻倒塌砸傷行人,需支付巨額賠償。公司派你去處理相關(guān)問(wèn)題,你應(yīng)該如何行動(dòng)?()查看答案
試題參考答案:C
試題解析與討論:www.xcpkj.com/st/4679012577.html
試題2
由于項(xiàng)目相關(guān)方對(duì)項(xiàng)目需求和關(guān)鍵可交付成果的意見(jiàn)不一致,項(xiàng)目經(jīng)理無(wú)法獲得項(xiàng)目發(fā)起人的范圍批準(zhǔn),若要獲得范圍批準(zhǔn),項(xiàng)目經(jīng)理應(yīng)該怎么做?查看答案
試題參考答案:C
試題解析與討論:www.xcpkj.com/st/4610523260.html
試題3
A project sponsor decides to add a feature to the project that affects the project cost, schedule,and scope. The change is approved by the change control board. Which process govern s the project manager's implementation of the approved change?()查看答案
試題參考答案:C
試題解析與討論:www.xcpkj.com/st/4905126756.html
試題4
一個(gè)新項(xiàng)目的項(xiàng)目經(jīng)理獲得四名必要授權(quán)發(fā)起人中三人的簽署同意,第四名項(xiàng)目發(fā)起人將在兩周內(nèi)度假回來(lái)。項(xiàng)目經(jīng)理應(yīng)該怎么做?查看答案
試題參考答案:D
試題解析與討論:www.xcpkj.com/st/4692620264.html
試題5
你正在管理來(lái)自兩個(gè)客戶的兩個(gè)不同項(xiàng)目。在和一名客戶會(huì)面的時(shí)候,你發(fā)現(xiàn)有一條敏感信息,可以幫助另外一名客戶節(jié)約大筆的項(xiàng)目預(yù)算。請(qǐng)問(wèn)你應(yīng)該怎么做?查看答案
試題參考答案:B
試題解析與討論:www.xcpkj.com/st/4731229279.html
試題6
問(wèn)題日志的用于∶查看答案
試題參考答案:B
試題解析與討論:www.xcpkj.com/st/4926711109.html
試題7
A project manager is developing the stakeholder engagement plan and identifying a stakeholder with a high level of power but low level of interest in the project. How should the project manager deal with this stakeholder?查看答案
試題參考答案:D
試題解析與討論:www.xcpkj.com/st/4791517031.html
試題8
項(xiàng)目團(tuán)隊(duì)和第三方供應(yīng)商簽訂合同,要求開(kāi)發(fā)指定的設(shè)備。第三方供應(yīng)商不希望接受項(xiàng)目期間成本增加的風(fēng)險(xiǎn),而項(xiàng)目團(tuán)隊(duì)希望盡量降低設(shè)備質(zhì)量差的風(fēng)險(xiǎn)。什么樣的合同類型對(duì)項(xiàng)目團(tuán)隊(duì)和第三方供應(yīng)商最有利?查看答案
試題參考答案:A
試題解析與討論:www.xcpkj.com/st/4886922410.html
試題9
To generate creative ideas during the Collect Requirements Process, the project manager solicits a group of experts through a series of questionnares,and whose answers are went directly back to the project manager. This technique is as know n as which of the following?查看答案
試題參考答案:A
試題解析與討論:www.xcpkj.com/st/481464953.html
試題10
由于不斷變化的立法項(xiàng)目團(tuán)隊(duì)識(shí)別到大量額外的需求.項(xiàng)目經(jīng)理要求團(tuán)隊(duì)針對(duì)每個(gè)需求提交變更請(qǐng)求,項(xiàng)目經(jīng)理下一步應(yīng)該怎么做?查看答案
試題參考答案:B
試題解析與討論:www.xcpkj.com/st/460914978.html
信管網(wǎng)訂閱號(hào)
信管網(wǎng)視頻號(hào)
信管網(wǎng)抖音號(hào)
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛(ài)好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過(guò)深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評(píng)論 查看完整評(píng)論 | |